Roof on & getting close to lock up
The sun has gone and we are getting ready for rain & hold ups due to the weather . Where are we at? ,Roof is on and we have been so busy...


March 2015 Brickwork complete
Late march 2015, still married and still on track. We have had a busy month with the brickwork going up & now complete , we can see space...


Feb 2015 Upper slab pour
We are into the second week of Feb, and things have been progressing smoothly and Drama free. Last week I went into see the lovely Ali @...


Getting ready to Sell
We are in the process of getting our Latour Street house ready to sell. To have a look at" Our before the Reno's photos " go to the "...


Christmas 2014
Christmas 2014 & the tradies have left for their break. Over the last few weeks things have been moving along at a great pace, the...


We have a start !
Since my last post there has been a considerable amount of progress. The plans have all been cleared with shire. Site works have begun....


Plans Off to Shire
Things are moving but very slowly, We have power to the block and our plans have been submitted to shire . There is a small anticipated...


Waiting & Waiting
Waiting Waiting Well its been 4 weeks since signing the contract with our builder Simon and we wait patiently for the bank to value...


So what are our Priorities ??
So what were we both looking for, Our first and most important priority was to build a home that was comfortable, inviting and somewhere...


The Beginning
As i sit here , with no idea how to write a blog, I’m guessing the best tactic is to start at the beginning and muddle my way through it...